What is the equivalent annual cost for a project that requires a $30,000 investment at...

70.2K

Verified Solution

Question

Finance

image

What is the equivalent annual cost for a project that requires a $30,000 investment at time-period zero, and a $8,000 annual expense during each of the next 4 years, if the opportunity cost of capital is 10 percent? $20,000.00 $17,464.12 $22,618.83 $23,237.15

Answer & Explanation Solved by verified expert