The actual cost of direct labour per hour is $13.00. Two standard direct labour hours...

60.1K

Verified Solution

Question

Accounting

The actual cost of direct labour per hour is $13.00. Two standard direct labour hours are allowed per finished good. During the current period, 2,000 finished goods were produced using 3,800 direct labour hours. The direct labour efficiency variance is $1,300, favourable. Which one of the following amounts is the standard direct labour rate per hour for the period?.

A.

$6.50

B.

$10.00

C.

$13.00

D.

$26.00

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students