please show work. 2. Since Jack believes that Work Center 3 is his bottleneck, he has asked you...

70.2K

Verified Solution

Question

Advance Math

pleaseshow work.

2. Since Jack believes that Work Center 3 is his bottleneck, he hasasked you to do the following:
a)Calculate the percentage of planned output needed to complete theplanned inputs (planned input + backlog/ planned output) at WorkCenter 3.
b)Calculate the percentage of planned input that actually happened (actual input + backlog/planned input + backlog).

information needed to answer the question above.

Jack, the owner and manager of Jack’s Box Company, wants to monitorusage at Work Center 3, which is a bottleneck in the system. He hascollected data on the planned and actual input and output.
Input Information (in hours)
4
5
6
7
8
Planned input
40
50
50
60
60
Actual input
45
45
45
55
60
Deviation
Cumulative deviation
Output Information (in hours)
4
5
6
7
8
Planned output
70
70
70
70
70
Actual output
60
60
60
60
60
Deviation
Cumulative deviation
Backlog 75 hours

a) Complete the input/output record.
b) Describe your concerns based on the results of the input/outputanalysis.

Answer & Explanation Solved by verified expert
4.2 Ratings (795 Votes)
    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students