Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table.

Job

Processing Time (days)

Days Due from Today

A

11

35

B

10

39

C

7

34

D

8

42

E

12

40

Using the shortest processing time (SPT) rule, it can be concluded that the average tardiness for the five jobs is:

a. more than 1.2 but less than or equal to 1.5 days.
b. more than 1.5 but less than or equal to 1.7 days.
c. more than 1.7 but less than or equal to 1.9 days.
d. more than 1.9 but less than or equal to 2.1 days.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students