Construction cost of a wastewater treatment plant is:C=1,300,000*Q^0.65, where Q is the capacity of the...

90.2K

Verified Solution

Question

Accounting

Construction cost of a wastewater treatment plant is:C=1,300,000*Q^0.65, where Q is the capacity of the plant in million gallons per day, MGD, and C is in dollars.

Demand for plant capacity increases linearly from zero today at 1 MGD per year.

Under the assumption of either 1 or 4 plant expansions (120 MGD or 45 MGD) will occur for the next 20 years, determine the break-even interest rate at which the cost of one expansion exactly equals that of four expansions.

Plot the break-even chart.

Which plant should the city choose should the interest rate be 6%?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students