activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D A,E 12 18 24 E - 8 10 18 F A,E 4 6 8 G B,F 7 8 9 H G 10 12 14 I G 5 6 7 J D,I 5 7 9 Calculate the probability of completing the project between 35 and 40 weeks?...

90.2K

Verified Solution

Question

General Management

activityfollowsoptimistic durationmost likely directionpessimistic duration
A-4614
BA,C345
C-3513
DA,E121824
E-81018
FA,E468
GB,F789
HG101214
IG567
JD,I579

Calculate the probability of completing the project between 35and 40 weeks? [4 pts]
  
f Answer the project manager’s question: “I want to tell the clientthat there is a 10.03% chance the project will take longer than Xweeks - what figure should I give them (i.e. find X)?”[4]

Answer & Explanation Solved by verified expert
3.8 Ratings (541 Votes)
We need to calcuate the project duration using the critical pathmethod PERT The expected duration isE optimistic 4most likely    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students