John’s Construction has three projects under way. Each projectrequires a regular supply of gravel, which can be obtained fromthree quarries. Shipping costs differ from location to location,and are summarized in the table.

From:Job 1Job 2Job 3Tonnage allowance
Quarry A$9$8$71500
Quarry B$7$11$61750
Quarry C$4$3$122750
Job Requirements (tonnes)2000300010006000

Formulate a transportation model (but do not attempt to solveit) which could be used to determine the amount of gravel to beshipped from each quarry to the various job sites.

Answer & Explanation Solved by verified expert
3.9 Ratings (680 Votes)
Let the amount of gravel from Quarry A to Job 1 In tonnes Let the amount of gravel from Quarry A to Job 2 In tonnes Let the amount of gravel from Quarry A to Job 3    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students