71) Use the information in the table and assume that a worker is expected to...
70.2K
Verified Solution
Link Copied!
Question
Accounting
71) Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis. If the project manager is told that the total number of hours per week cannot exceed 48, what is the first week that some resource leveling must occur?
Activity
Predecessor
Hours per Day
Time (Days)
A
--
4
6
B
A
4
11
C
A
5
5
D
B
4
6
E
B
4
6
F
B
6
3
G
C, D
8
11
H
E, F
8
8
J
G, H
3
10
K
J
6
4
A) Week 2
B) Week 6
C) Week 4
D) Week 5
72) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks. What is the fastest the project can be completed?
Activity
Activity time
Workers Needed
Predecessor
A
10
1
B
4
2
C
7
3
A
D
4
1
A
E
8
2
B
F
9
3
C,E
G
13
1
D
H
14
2
E,G
J
13
3
F
K
10
1
H, J
L
5
2
K
A) 54 days
B) 56 days
C) 58 days
D) 60 days
73) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What is the fastest the project can be completed while constrained by the four worker limitation?
Activity
Activity time
Workers Needed
Predecessor
A
10
1
B
4
2
C
7
3
A
D
4
1
A
E
8
2
B
F
9
3
C,E
G
13
1
D
H
14
2
E,G
J
13
3
F
K
10
1
H, J
L
5
2
K
A) 68 days
B) 70 days
C) 66 days
D) 72 days
74) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What is the first day where this project exceeds the four worker maximum?
Activity
Activity time
Workers Needed
Predecessor
A
10
1
B
4
2
C
7
3
A
D
4
1
A
E
8
2
B
F
9
3
C,E
G
13
1
D
H
14
2
E,G
J
13
3
F
K
10
1
H, J
L
5
2
K
A) Day 10
B) Day 11
C) Day 12
D) Day 13
75) A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What day does activity C start under a leveled project with the four worker limitation?
Activity
Activity time
Workers Needed
Predecessor
A
10
1
B
4
2
C
7
3
A
D
4
1
A
E
8
2
B
F
9
3
C,E
G
13
1
D
H
14
2
E,G
J
13
3
F
K
10
1
H, J
L
5
2
K
A) Day 13
B) Day 15
C) Day 17
D) Day 19
Show explanation
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!