1) Find out the standard time using the following data: Average time for machine elements = 6...

60.1K

Verified Solution

Question

Mechanical Engineering

1) Find out the standard time using the following data:

Average time for machineelements = 6 min.

Average time for manual elements = 4min.

Performance rating = 110%

Allowances = 10% of normal time

2) The actual observed time for anoperation was 1 minute per piece. If the performance rating of theoperator was 120 and a 5 per cent personal time is to be provided,the standard time in minute per piece is:

Answer & Explanation Solved by verified expert
4.4 Ratings (682 Votes)
Q 1 Input 1 Avg time for machine elements 6 min 2 Avg time for manual elements 4 min 3 Performace rating 110 4 Allowance 10 normal time To find Standard time Answer Let us find out Normal time    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students