Question

Finance

ZZZ inc. would like to implement a new project. It is estimated that the projects costs at t=0 will

be $1,000,000, it will generate the following cash flows: C1=$500,000; C2=$300,000;

C3=$200,000; C4=$150,000; C5=$75,000; C6=$50,000; The cost of capital (discount rate) is 10%

Find the projects profitability index

Find the projects EEA