Your project to deliver a product has five activities, each with a finish-to-start relationship. Project...
90.2K
Verified Solution
Question
Accounting
Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.
Baseline
Activity Name | Start (Baseline) | Finish (Baseline) | Cost (Baseline) |
Product | 6/2/14 | 5/25/15 |
|
Requirements | 6/2/14 | 8/22/14 | 60,000.00 |
Design | 8/25/14 | 11/14/14 | 90,000.00 |
Build | 11/17/14 | 3/20/15 | 120,000.00 |
Test | 3/23/15 | 5/22/15 | 50,000.00 |
Release | 5/25/15 | 5/25/15 | 0.00 |
You have to report project status as of January 30, 2015. The associated schedule and cost information is provided below. Assume: (1) a five-day work week; and (2) a constant resource loading (i.e., the rate of planned expenditures is constant over the duration of each activity).
Actual
Activity Name | % Complete | Start (Actual) | Finish (Actual) | Cost (Actual) |
Product |
| 6/2/14 | NA |
|
Requirements | 100 | 6/2/14 | 8/30/14 | 68,000 |
Design | 100 | 8/31/14 | 11/20/14 | 85,000 |
Build | 70 | 11/21/14 | NA | 110,000 |
Test | 0 | NA | NA | 0 |
Release | 0 | NA | NA | 0 |
Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.
- Earned Value Measures
- Calculate earned value measures for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
Requirements |
|
| 68,000 |
Design |
|
| 85,000 |
Build |
|
| 110,000 |
Test |
|
| 0 |
Release |
|
| 0 |
Entire Project |
|
|
|
-
- What is the Budget at Completion (BAC) for the project?
- Earned Value Performance Measures
- Calculate earned value performance parameters for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity | Schedule Variance (SV) | Schedule Performance Index (SPI) | Cost Variance (CV) | Cost Performance Index (CPI) |
Requirements |
|
|
|
|
Design |
|
|
|
|
Build |
|
|
|
|
Test |
|
|
|
|
Release |
|
|
|
|
Entire Project |
|
|
|
|
-
- Is the project ahead of schedule, on schedule, or behind schedule? Why?
- Is the project over budget, under budget, or on budget? Why?
- Earned Value Forecasts
- Assuming the Cost Performance Index (CPI) remains constant for the remainder of the project:
- What is the Estimate at Completion (EAC)?
- What is the Estimate-to-Complete (ETC)?
- How much more or less money (other than the current budgeted amount) will you need to finish the project?
- How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?
- Assuming the Cost Performance Index (CPI) remains constant for the remainder of the project:
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.