Your company is evaluation 4 independent projects and is subject to capital rationing, detailed as...
70.2K
Verified Solution
Question
Finance
Your company is evaluation 4 independent projects and is subject to capital rationing, detailed as follows:
Project Initial Outlay IRR NPV
1 2 million 18% 2,500,000
2 1 million 15% 950,000
3 1 million 10% 600,000
4 3 million 9% 2,000,000
If you must select projects subject to a budget constraint of 3 million dollars, which set of projects should be accepted so as to maximize firm value?
1 and 2 | ||
1 only | ||
1, 2 and 3 | ||
1 and 4 | ||
2, 3 and 4 |
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.