You may need to use the appropriate technology to answer this question. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown.

Activity Immediate Predecessor Optimistic Most Probable Pessimistic
A 3 5 6
B 2 4 6
C A,B 4 5 6
D A,B 8 10 11
E B 2 4 6
F C 1 2 3
G D 4 9 11
H D, F 5 7 9
I E,G,H 3 4 5

(a) What are the critical activities? (Enter your answers as a comma-separated list.) (b) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (c)Based only on the critical path, what is the estimated probability that the project can be completed in 27 or fewer days? (Round your answer to four decimal places.)

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students