You have monitored cost budget and earned values for each activity or project What is the status of the project to date?
1 AC 65,000 EV 62,000 BV 67,000
2 AC 85,000 EV 79,000 BV 89,000
3 AC 100,000 EV 102,000 BV 110,000
4 AC 125,000 EV 124,000 BV 123,000
5 AC 125,000 EV 123,000 BV 131,000
A The project ahead of schedule and under budget
B The project is behind schedule and under budget
C the project is ahead of schedule and over budget
D the project is ahead of shecule and under budget
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.