You are managing an eight-month project with a BAC of $100K. On Friday afternoon, at...

60.1K

Verified Solution

Question

Accounting

You are managing an eight-month project with a BAC of $100K. On Friday afternoon, at the end of the fourth month (half way through the project), your EVM system provides the following values:

BCWS=$50K BCWP = $55k ACWP = $75k Your boss asks you to present the EAC at the Monday morning status meeting. You have been an attentive project manager and you have been especially pleased that the BCWP has been tracking quite well to the BCWS. Below are listed three possible answers one might provide as the EAC.

For each possible answer, first list any assumptions necessary and then provide the rationale and analysis, which would justify or explain it.

$100k:

$125k:

$150k:

Having done the analysis and considered the explanations for each of these answers, which answer would you be most comfortable presenting to your boss? Why?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students