You are managing a telecommunications project. The project is expected to be completed in 10...

50.1K

Verified Solution

Question

Accounting

You are managing a telecommunications project. The project is expected to be completed in 10 months at a cost of $12000 per month. After 2 months, you realize that the project is 30% completed at a cost of $60,000. What are the Earned Value (EV) and the Cost Variance (CV)?

Answer & Explanation Solved by verified expert