You are managing a project with a budget of 500,000 USD, and 250,000 USD has been spent. Upon review, you observe that only 40% of the work has been completed. Your schedule says that you should have completed 50% of the work. What is estimate at completion (EAC)? Group of answer choices (c) 400,000 USD (d) 375,000 USD (a) 625,000 USD (b) 500,000 USD