You are managing a constructions project. You have completed half the project work. The total...

80.2K

Verified Solution

Question

Accounting

You are managing a constructions project. You have completed half the project work. The total planned cost at this stage is $10000. The actual work that has been completed at this stage is worth $6200. You have spent $6500 already on the project. What is the CPI?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students