You are constructing a building for a client who is in control of the asset during the term of the contract. So as a brilliant accountant you already know, since the client controls the asset during the project, you need to use the percentage completion method to recognize revenue for this project. The contract is worth $10,847,600. Other items of interest Estimated Costs = $8,769,200
Actual costs for 2015 and 2016 were perfectly estimated
Someone underestimated costs for 2017 by $146,800
Year | Construction Costs ($) | Billing the customer ($) |
2015 | 2,674,800 | 2,278,500 |
2016 | 4,458,000 | 4,854,200 |
2017 | 1,783,200 | 3,714,900 |
Now assume the client did not maintain control of the asset during construction.
Prepare the journal entries for revenue recognition for 2017 ONLY!
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.