You are building a bus stop shelter and have been working on it for 20 days....

70.2K

Verified Solution

Question

Operations Management

You are building a bus stop shelter and have been working on itfor 20 days. Your boss has asked for a status report for theproject after 20 days.

a) Fill in the missing values in the following StatusReport.

b) For the entire project, what is the current

a. Cost Performance Index, CPI = ________,

b. Schedule Performance Index, SPI = _________,

c. Cost Variance, CV = _________,

d. Schedule Variance, SV = __________.

c) Suppose that the work from this date forward will progress atplanned rates whether or not these rates have prevailed to date.What is the forecasted cost at completion (FAC) for the entireproject?

itemtotal budget($)planned progressBCWS($)ACWP($)ACTUAL PROGRESSBCWP($)CVSVFAC($)
excavation9600100%9000100%
cast slab1800100%2000100%
curb1500100%1500100%
walls270080%2500100%
paving120040%30020%
roof trusses100040%50060%
roofing60010%00%
lights50020%25040%
seating5000%00%
paint10000%00%

Answer & Explanation Solved by verified expert
4.1 Ratings (474 Votes)
We complete the given table as shown belowThe columns highlighted in green are calculated by usThe above table in the form of formulas is    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students