You are a manager at Percolated Fiber, which is considering expanding its operations in synthetic...

80.2K

Verified Solution

Question

Finance

You are a manager at Percolated Fiber, which is considering expanding its operations in synthetic fiber manufacturing. Your boss comes into your office, drops a consultant's report on your desk, and complains, "We owe these consultants $1.2 million for this report, and I am not sure their analysis makes sense. Before we spend the $15 million on new equipment needed for this project, look it over and give me your opinion." You open the report and find the following estimates (in millions of dollars):

Project Year

Earnings Forecast ($ million)

1

2

. . .

9

10

Sales revenue

32.000

32.000

32.000

32.000

Cost

of goods sold

19.200

19.200

19.200

19.200

=Gross

profit

12.800

12.800

12.800

12.800

Selling,

general, and administrative expenses

1.200

1.200

1.200

1.200

Depreciation

1.500

1.500

1.500

1.500

=Net

operating income

10.100

10.100

10.100

10.100

Income

tax

2.02

2.02

2.02

2.02

=Net

unlevered income

8.080

8.080

8.080

8.080

All of the estimates in the report seem correct. You note that the consultants used straight-line depreciation for the new equipment that will be purchased today (year 0), which is what the accounting department recommended. The report concludes that because the project will increase earnings by $8.080 million per year for ten years, the project is worth $80.8 million. You think back to your halcyon days in finance class and realize there is more work to be done!

First, you note that the consultants have not factored in the fact that the project will require $14 million in working capital upfront (year 0), which will be fully recovered in year 10. Next, you see they have attributed $1.2 million of selling, general and administrative expenses to the project, but you know that $0.6 million of this amount is overhead that will be incurred even if the project is not accepted. Finally, you know that accounting earnings are not the right thing to focus on!

a. Given the available information, what are the free cash flows in years 0 through 10 that should be used to evaluate the proposed project?

b. If the cost of capital for this project is 12%, what is your estimate of the value of the new project?

Questions:

a. Given the available information, what are the free cash flows in years 0 through 10 that should be used to evaluate the proposed project?

The free cash flow for year 0 is $???? million. (Round to three decimal places and enter a decrease as a negative number.)

The free cash flow for years 1 to 9 is $???? million. (Round to three decimal places and enter a decrease as a negative number.)

The free cash flow for year 10 is $????? million. (Round to three decimal places and enter a decrease as a negative number.)

b. If the cost of capital for this project is 8%, what is your estimate of the value of the new project?

The value of the project is $????? million. (Round to three decimal places.)

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students