6. What is each projects initial NPV without replication?

7. What is each projects equivalent annual annuity?

8. Now apply the replacement chain approach to determine the shorter projects extended NPV. Which project should be chosen?

9. Now assume that the cost to replicate Project Y in 2 years will increase to $140,000 because of inflationary pressures. How should the analysis be handled now, and which project should be chosen?

10. You are also considering another project which has a physical life of 3 years; that is, the machinery will be totally worn out after 3 years. However, if the project were terminated prior to the end of 3 years, the machinery would have a positive salvage value. Here are the projects estimated cash flows:

Yr

CF

Salvage

0

($57,000)

$57,000

1

26,200

38,000

2

32,800

19,000

3

49,525

0

Using the 12% cost of capital, what is the projects NPV if it is operated for the full 3 years? Would the NPV change if the company planned to terminate the project at the end of Year 2? At the end of Year 1? What is the projects optimal (economic) life?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students