Wolseleys dilemma of Traditional Costing versus Activity Based Costing Wolseley Manufacturing Corporation manufactures various...
50.1K
Verified Solution
Link Copied!
Question
Accounting
Wolseleys dilemma of Traditional Costing versus Activity Based Costing
Wolseley Manufacturing Corporation manufactures various electronics products and follows a traditional (job-order) costing system in which it applies manufacturing overhead to its products using a predetermined overhead rate based on direct labour-hours (DLHs). The company has two products, C18R and G19R, about which it has provided the following data:
C18R
G19R
Direct materials per unit
$10.20
$50.50
Direct labour per unit
$8.40
$25.20
Direct labour hours per unit
0.40
1.20
Annual production
30,000
10,000
The company's estimated total manufacturing overhead for the year is $1,464,480 and the company's estimated total direct labour-hours for the year is 24,000. The company is considering using a variation of activity-based costing to determine its unit product costs for external reports. Data for this proposed activity-based costing system appear below:
Activities and Activity Measures
Estimated Overhead Cost
Supporting direct labour (DLHs)
$552,000
Setting up machines (setups)
132,480
Parts administration (part types)
780,000
Total
$1,464,480
Activities
C18R
G19R
Total
Supporting direct labour
12,000
12,000
24,000
Setting up machines
864
240
1,104
Part administration
600
960
1,560
Mike, who is the controller of the Company, is currently overseeing the project to switch from traditional costing to Activity-Based costing. He is in a meeting with the Cost Accountant of the company. The Controller goes over the data and makes the following comments:
Activity-Based Costing is a revelation in the modern-day world of manufacturing Industry. If we are correctly able to categorize the various nature of work into essential levels, then we can dramatically trace the precise nature of the overheard activity.
Jacob, the Cost Accountant, quips, how can we classify those levels of activities? Do we have some mechanism to identify them?
Mike responds, Yes! We do.
Jacob then laments the pitfalls of the job order costing system, The production report will be out soon and usually, the allocation bases (including overhead allocations in job-order costing systems) are not entirely accurate. Mike, with a pause, That is exactly why we may eventually need to switch to the Activity-Based costing though it is comparatively difficult to implement with the cost and operations limitations involved in it.
Jacob adds, Another consideration to evaluate is the relationship between the cost of maximum (budgeted) capacity and idle capacity, since the company is likely to operate at maximum capacities during the time of peak demand. Moreover, our long-term goals of stable cost predictions and waste minimizations should also be kept in mind.
Alright! Let us calculate and analyze the quantitative and qualitative aspects of the data and other factors we have discussed in the meeting today and prepare the preliminary report for the CEO by this weekend. Mike with the final comments!
Enable GingerCannot connect to Ginger Check your internet connection or reload the browserDisable in this text fieldRephraseRephrase current sentence11Edit in Ginger
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!