Windsor Construction Company has entered into a contract beginning January 1,2020, to build a parking...

80.2K

Verified Solution

Question

Accounting

Windsor Construction Company has entered into a contract beginning January 1,2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period.
202020212022
Costs to date $260,580 $446,620 $618,000
Estimated costs to complete $345,420 $139,380 $0
Progress billings to date $272,000 $551,000 $891,000
Cash collected to date 242,000501,000891,000
(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $
(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.
Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students