Question

Accounting

Why is the auditor more concerned with the risk of assessing control risk too low rather than the risk of assessing control risk too high?

The risk of assessing control risk too high is not a type of sampling risk.

The risk of assessing control risk too low exposes the auditor to an efficiency loss.

The risk of assessing control risk too low may result in the auditor failing to perform sufficient substantive procedures.

The risk of assessing control risk too low cannot be measured by the auditor during the sampling process.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students