Which is not a part of the time management A. Plan Schedule Management B. Define Activities C. Control...

60.1K

Verified Solution

Question

General Management

Which is not a part of the time management

A. Plan Schedule Management

B. Define Activities

C. Control Activates

D. Sequence Activities

Answer & Explanation Solved by verified expert
3.9 Ratings (730 Votes)
The answer is C Control Activities Time Management as per PMI is currently coined Schedule Management Plan schedule managment is the process in which you plan for how to make the plan It details the    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students