Which is correct about the following: A)It is under budget and behind schedule. B)It is...

50.1K

Verified Solution

Question

Accounting

Which is correct about the following:

A)It is under budget and behind schedule.

B)It is over budget and ahead of schedule

C)It is under budget and ahead of schedule.

D)It is over budget and behind schedule.

image

AC=1,345,000 PU=1,200.000 EV=1,135,000

Answer & Explanation Solved by verified expert