Which combination of True and False is correct?1) In making a forward pass through a network, three activities are immediate predecessors for activity T. The early start time for activity T is the largest EF for the three activities that are immediate predecessors for activity T.2) In critical path scheduling, slack is computed as the difference between finish and start times.Select one:a. 1) True and 2) Trueb. 1) False and 2) Falsec) True and 2) Falsed 1) False and 2) True