When job 711 was completed, direct materials cost totaled $4,000; direct labor cost totaled $4,600; and factory overhead cost totaled $2,400. Units produced totaled 1,000. The cost per unit is equal to: a) $11,000 b) $11 c) $110 d) $1,100