What was the direct labor flexible budget variance for 2014 (a positive number means a...

50.1K

Verified Solution

Question

Accounting

What was the direct labor flexible budget variance for 2014 (a positive number means a favorable variance; a negative number means an unfavorable variance)?

Budgeted hours per unit 4
Budgeted hourly wage rate $13.00
Budgeted production 4840
Actual production 5450
Actual cost $185,000