W QUESTION COMPLETION STATUS: Question 21 Dol 1 points The following represents a project with...

60.1K

Verified Solution

Question

Accounting

image
W QUESTION COMPLETION STATUS: Question 21 Dol 1 points The following represents a project with known activity times. All times are in weeks Predecessors Time & Activity B D E F 6 4 B CD B 14 10 What is the estimated time to complete the project? O s. 28 weeks b. 22 weeks Oc 16 weeks d. 50 weeks