Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two...

50.1K

Verified Solution

Question

Accounting

Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands).

2020 2021 2022
Costs for the year $3,825 4,675 1,200
Estimated costs to complete 4,675 1,270 -0-
Progress billings for the year (non-refundable) 3,500 4,100 2,400
Cash collected for the year 3,100 4,150 2,750

Using the percentage-of-completion method, calculate the percent complete for each year of the contract.

2020:

2021:

2022:

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students