Two-Stage ABC for Manufacturing Columbus Foundry, a large manufacturer of heavy equipment components, has determined...

50.1K

Verified Solution

Question

Accounting

Two-Stage ABC for Manufacturing Columbus Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year:

Activity cost pool Activity cost Activity cost driver
Machine setup $600,000 12,000 setup hours
Material handling 120,000 2,000 tons of materials
Machine operation 500,000 10,000 machine hours

The following data are for the production of single batches of two products, C23 Cams and U2 Shafts:

C23 Cams U2 Shafts
Units produced 500 500
Machine hours 2 5
Direct labor hours 400 200
Direct labor cost $5,000 $10,000
Direct materials cost $30,000 $20,000
Tons of materials 12.5 8
Setup hours 4 9

Determine the unit costs of C23 Cams and U2 Shafts using ABC. C23 Cams $? U2 Shafts $?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students