Two contractors submitted the following cost estimates for a proposed bridge: Bridge A...
90.2K
Verified Solution
Question
Accounting
Two contractors submitted the following cost estimates for a proposed bridge:
Bridge A Bridge B
First Cost P20M P27M
Life 20 years 30 years
Salvage Value P500,000 P750,000
Annual Upkeep P160,000 P50,000
Repairs P1.5M every 4 years P1M every 6 years
If interest is 7.5% compounded annually, which bridge is cheaper in terms of its capitalized cost? and by how much?
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.