Two companies process equipment differently C1 for company 1 and C2 for company 2. Calculate cost of parts for each process. (P1,P2)
beakeven point is 80 parts
costs $14000 to manufacture parts from C2
to setup processes it costs 5000 for C1 and 2000 for C2