Trico Company set the following standard unit costs for its single product. ...
70.2K
Verified Solution
Question
Accounting
Trico Company set the following standard unit costs for its single product. |
Direct materials (26 Ibs. @ $3.00 per Ib.) | $ | 78.00 |
Direct labor (6 hrs. @ $6.00 per hr.) | 36.00 | |
Factory overheadvariable (6 hrs. @ $4.00 per hr.) | 24.00 | |
Factory overheadfixed (6 hrs. @ $5.00 per hr.) | 30.00 | |
Total standard cost | $ | 168.00 |
The predetermined overhead rate is based on a planned operating volume of 60% of the productive capacity of 50,000 units per quarter. The following flexible budget information is available. |
Operating Levels | ||||||
50% | 60% | 70% | ||||
Production in units | 25,000 | 30,000 | 35,000 | |||
Standard direct labor hours | 150,000 | 180,000 | 210,000 | |||
Budgeted overhead | ||||||
Fixed factory overhead | $ | 900,000 | $ | 900,000 | $ | 900,000 |
Variable factory overhead | $ | 600,000 | $ | 720,000 | $ | 840,000 |
During the current quarter, the company operated at 70% of capacity and produced 35,000 units of product; actual direct labor totaled 204,000 hours. Units produced were assigned the following standard costs: |
Direct materials (910,000 Ibs. @ $3.00 per Ib.) | $ | 2,730,000 |
Direct labor (210,000 hrs. @ $6.00 per hr.) | 1,260,000 | |
Factory overhead (210,000 hrs. @ $9.00 per hr.) | 1,890,000 | |
Total standard cost | $ | 5,880,000 |
Actual costs incurred during the current quarter follow: |
Direct materials (905,000 Ibs. @ $3.10) | $ | 2,805,500 |
Direct labor (204,000 hrs. @ $5.75) | 1,173,000 | |
Fixed factory overhead costs | 1,809,057 | |
Variable factory overhead costs | 1,693,585 | |
Total actual costs | $ | 7,481,142 |
rev: 01_19_2015_QC_CS-3499
References
Section BreakProblem 23-1A Computation of materials, labor, and overhead variances LO P2, P3
44.
value: 5.00 points
Required information
Problem 23-1A Part 1
Required: | |
1. | Compute the direct materials cost variance, including its price and quantity variances.(Round actual price to 2 decimal places.) |
References
eBook & Resources
Expanded tableDifficulty: HardLearning Objective: 23-P3 Compute overhead variances.
Problem 23-1A Part 1Learning Objective: 23-P2 Compute materials and labor variances.
45.
value: 5.00 points
Required information
Problem 23-1A Part 2
2. | Compute the direct labor variance, including its rate and efficiency variances.(Round actual rate to 2 decimal places.) |
References
eBook & Resources
Expanded tableDifficulty: HardLearning Objective: 23-P3 Compute overhead variances.
Problem 23-1A Part 2Learning Objective: 23-P2 Compute materials and labor variances.
46.
value: 5.00 points
Required information
Problem 23-1A Part 3
3. | Compute the overhead controllable and volume variances. |
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.