Tom's Reclaimers entered into a contract with Daniel's Demolition to manage the processing of
recycled materials on Daniel's various demolition projects. Services for the year contract
include collecting, sorting, and transporting reclaimed materials to recycling centers or
contractors who will reuse them. Tom's incurs selling commission costs of $ to obtain the
contract. Before performing the services, Tom's also designs and builds receptacles and loading
equipment that interfaces with Daniel's demolition equipment at a cost of $ These
receptacles and equipment are retained by Tom's and can be used for other projects. Daniel's
promises to pay a fixed fee of $ per year, payable every months for the services under the
contract. Tom's incurs the following costs: design services for the receptacles to interface with
Daniel's equipment $ loading equipment controllers $ and special testing and OSHA
inspection fees $some of Daniel's projects are on government property
Determine the costs that should be capitalized as part of Tom's Reclaimers revenue
arrangement with Daniel's Demolition. If answer is please enter Do not leave any fields
blank.
Commission costs $
Design services $
Cost of loading equipment controllers $
Inspection fees $
Receptacles and loading equipment