Question

Accounting

This is due tonight and i still cant manage to get it solved. please help

This was all the information that i was given

Figure 3-2 to accompany Table 3.2

image

Table 3.2

ACTIVITY NORMAL TIME CRASH TIME NORMAL COST ($000s) CRASH COST ($000s) AVAILABLE WEEKS OF CRASHING CRASHING COST / WEEK
A 4 2 8 14
B 3 2 9 11
C 4 4 10 10
D 5 3 10 15
E 4 1 11 14
F 1 1 6 6

1) What is the critical path for the project shown in the above network and Table 3.2, using the normal times?

A) A-B-D-F

B) A-C-D-F

C) A-C-E-F

D) A-B-C-D-E-F

2) Determine the information missing from Table 3.2; then answer the following questions. How many week(s) of crashing are available for activity D in Table 3.2?

A) 0

B) 1

C) 2

D) 6

3) How many week(s) of crashing are available for activity B in Table 3.2?

A) 0

B) 1

C) 2

D) 3

4) How many weeks of crashing are available for activity C in Table 3.2?

A) 0

B) 1

C) 2

D) 6

5) What is the crashing cost per week for activity A in Table 3.2?

A) $2,000

B) $3,000

C) $4,000

D) This activity cannot be crashed.

6) What is the crashing cost per week for activity E in Table 3.2?

A) $1,000

B) $2,000

C) $3,000

D) This activity cannot be crashed.

7) What is the crashing cost per week for activity F in Table 3.2?

A) $2,000

B) $3,000

C) $4,000

D) This activity cannot be crashed.

8) If a decision is made to crash activity D in Table 3.2 by one week, what is the cost for this one week of crashing? (3 points)

A) $3,000

B) $2,000

C) $2,500

D) This activity cannot be crashed.

9) Which activity should be crashed first for the project shown in Table 3.2? (3 points)

A) A

B) B

C) C

D) D

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students