Question
Accounting
This is due tonight and i still cant manage to get it solved. please help
This was all the information that i was given
Figure 3-2 to accompany Table 3.2
Table 3.2
ACTIVITY | NORMAL TIME | CRASH TIME | NORMAL COST ($000s) | CRASH COST ($000s) | AVAILABLE WEEKS OF CRASHING | CRASHING COST / WEEK |
A | 4 | 2 | 8 | 14 | ||
B | 3 | 2 | 9 | 11 | ||
C | 4 | 4 | 10 | 10 | ||
D | 5 | 3 | 10 | 15 | ||
E | 4 | 1 | 11 | 14 | ||
F | 1 | 1 | 6 | 6 |
1) What is the critical path for the project shown in the above network and Table 3.2, using the normal times?
A) A-B-D-F
B) A-C-D-F
C) A-C-E-F
D) A-B-C-D-E-F
2) Determine the information missing from Table 3.2; then answer the following questions. How many week(s) of crashing are available for activity D in Table 3.2?
A) 0
B) 1
C) 2
D) 6
3) How many week(s) of crashing are available for activity B in Table 3.2?
A) 0
B) 1
C) 2
D) 3
4) How many weeks of crashing are available for activity C in Table 3.2?
A) 0
B) 1
C) 2
D) 6
5) What is the crashing cost per week for activity A in Table 3.2?
A) $2,000
B) $3,000
C) $4,000
D) This activity cannot be crashed.
6) What is the crashing cost per week for activity E in Table 3.2?
A) $1,000
B) $2,000
C) $3,000
D) This activity cannot be crashed.
7) What is the crashing cost per week for activity F in Table 3.2?
A) $2,000
B) $3,000
C) $4,000
D) This activity cannot be crashed.
8) If a decision is made to crash activity D in Table 3.2 by one week, what is the cost for this one week of crashing? (3 points)
A) $3,000
B) $2,000
C) $2,500
D) This activity cannot be crashed.
9) Which activity should be crashed first for the project shown in Table 3.2? (3 points)
A) A
B) B
C) C
D) D
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.