Question

Civil Engineering

There is a project with three activites planned for ayear (Units are in Rial)

• ‘Activity A’ with a planned cost of 2100,
• ‘Activity B’ with a planned cost of 1500 and
• ‘Activity C’ with a planned cost of 2500.
• Activity A turned out to be more expensive (with an additional300).
• ‘Activity B’ was done as budgeted.
• ‘Activity C’ is not finished within the year, and only 1500 wasspent on it.
• An additional activity ‘Activity D’ was needed and performed witha cost of 500.
What is the cost variance for the given year?Also write a detailedconclusion on the
cost performance

Answer & Explanation Solved by verified expert
4.4 Ratings (640 Votes)
Cost variance is the difference of budgeted cost of worksperformed BCWP and actual    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students