The variable cost per unit for a proposed project is $7.36 and the annual fixed...

90.2K

Verified Solution

Question

Finance

The variable cost per unit for a proposed project is $7.36 and the annual fixed costs are $25,800. These costs can vary by 3 percent. Annual depreciation is $12,970 and the tax rate is 21 percent. The sale price is $13 a unit, 2 percent. If the firm bases its sensitivity analysis on the expected outcome, what will be the operating cash flow for a sensitivity analysis of 10,000 units?

Don't round steps. 2 decimal answer.

OCF for 10,000 units =

What will be the operating cash flow for a sensitivity analysis of 9,900 units?

Don't round steps. 2 decimal answer.

OCF for 9,900 units =

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students