The total cycle time of an automatied fiber placement (AFP) operation (sheet lamination), used to manufacture...

50.1K

Verified Solution

Question

Mechanical Engineering

The total cycle time of an automatied fiber placement (AFP)operation (sheet lamination), used to manufacture a section of theairplane fuselage, is 8 hours and 40 minutes. The setup time beforethe start of the operation is 10 minutes. After each layer is putdown, an inspection stage is performed for 5 minutes. The AFP headrequires cleaning cycle of 3 minutes every 7 layers.

a. If the part is made of 20 layers, what is the time required(in minutes) to lay down 1 layer?

b. What is the percentage of down time for this operation?

c. What is the total cycle time (in minutes) for making thispart, if the lay down speed was doubled?

Answer & Explanation Solved by verified expert
3.7 Ratings (569 Votes)
Assumption It is assumed that cleaning is not performed at end ie end of 20th cycle this is because only 6 layers are deposited after last cleaning and    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students