the standard labor cost in the production of a pair of Tukor Brand athletic shoes...

70.2K

Verified Solution

Question

Accounting

the standard labor cost in the production of a pair of Tukor Brand athletic shoes is .40 at $13.00 per hour. During the month of June, 2500 pairs were produced. Actual labor costs were $111,700 for 8,200 hours. Compute the labor rate and labor efficency variances for the month of june