The Shady Farm Milk Company can process milk at a fixed rate of 5100 gallons/hour. The...

Free

80.2K

Verified Solution

Question

General Management

The Shady Farm Milk Company canprocess milk at a fixed rate of 5100 gallons/hour. The company’sclients request 94000 gallons of milk over the course of one day.This demand is spread out uniformly from 8 a.m. - 6 p.m. Thecompany starts producing at 8 a.m. and continues to work until allof the demand has been satisfied.
(Roundyour answer to 2 decimal places.)
How long does the clientrequesting milk at 6 p.m. have to wait to have their demandsatisfied?hours

Answer & Explanation Solved by verified expert
4.4 Ratings (638 Votes)

Waiting time for client at 6 p.m. = Available hours till 6 p.m. * (Demand per hour Capacity per hour – 1)

Here,

Available hours till 6 p.m. = 10 hours

Demand per hour = Gallons demanded per day Available hours in a day

                             = 94000 10

                             = 9400 gallons

Capacity per hour = 5100 gallons

So, Waiting time for client at 6 p.m. = 10 * ( 94005100 – 1)

                                                         = 8 hours (approximately)


Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students