The program office for a Navy shipboard communications system early in the TMRR phase just...
80.2K
Verified Solution
Question
Accounting
The program office for a Navy shipboard communications system early in the TMRR phase just conducted an affordability analysis of their key performance parameters.The program can save 10% on overall life cycle cost by trading 5% of point to point surface communications range KPP for greater component reliability.The Navy CDD sponsor agreed to include the requirements change as part of staffing for the CDD-V.For questions 6 through 9 (worth 3 points each), choose the greatest potential impact of the changed requirements on thegiven functional area(i.e., which is the greatest impact on Logistics, on T&E, on Funds Management etc.):
The greatest impact onLogisticswill be:
Answers:
a.
Changes to manufacturing methods
b.
Modification of the contract
c.
Additional testing to verify that new requirements are met without impacting other requirements
d.
Changes to maintenance and supply planning based on the new component
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.