The port operations staff in Izmir Port tries to make loadingschedule of a ship that will arrive on Monday. There are 6container yards in the port. The containers first must be picked upfrom each yard to shipment lane by a dedicated forklift. Secondlycontainers must be loaded on board from shipment lane by a specificcrane. The required times (in minutes) for each operation is asfollows; Yards Forklift Crane 1 15 45 2 55 60 3 26 75 4 9 50 5 2220 6 19 10 Determine how the loading of container at each yardshould be scheduled in order to minimize the total makespan. Pleasedraw the Gantt chart to show the optimal schedule and calculate themakespan.