The mean time required to complete a certain type of construction project is 52 weeks with...

90.2K

Verified Solution

Question

Basic Math

The mean time required to complete a certain type ofconstruction project is 52 weeks with a standard deviation of 3weeks. Answer questions 4–7 using the preceding information andmodeling this situation as a normal distribution.

  1. What is the probability of the completing the project in nomore than 52 weeks?
  1. 0.25
  2. 0.50
  3. 0.75
  4. 0.05
  1. What is the probability of the completing the project in morethan 55 weeks?
  1. 0.1587
  2. 0.5091
  3. 0.7511
  4. 0.0546
  1. What is the probability of completing the project between 56weeks and 64 weeks?
  1. 0.2587
  2. 0.3334
  3. 0.5876
  4. 0.0911
  1. What is the probability of completing the project within plusor minus one standard deviation of the mean?
  1. 0.951
  2. 0.852
  3. 0.759
  4. 0.683

Answer & Explanation Solved by verified expert
3.7 Ratings (563 Votes)
    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students