The material correction factor is 1.0. Assume slot dozing, and a 50 min/hr job efficiency. For...
70.2K
Verified Solution
Question
Civil Engineering
The material correction factor is 1.0. Assume slot dozing, and a50 min/hr job efficiency. For weight, wet sand is pretty close to2300 pounds per Cy. Excluding grade, what is my net correctionfactor for the other factors (excluding grade)?
The material correction factor is 1.0. Assume slot dozing, and a50 min/hr job efficiency. For weight, wet sand is pretty close to2300 pounds per Cy. Excluding grade, what is my net correctionfactor for the other factors (excluding grade)?
Answer & Explanation Solved by verified expert
3.9 Ratings (515 Votes)
Find the different correction factors for less than idealconditionsa Material weight Correction FactorCF
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.