The management of Vert Lawnmowers has calculated the following variances:
Direct materials cost variance $8,000 U
Direct materials efficiency variance 38,000 F
Direct labor cost variance 17,000 F
Direct labor efficiency variance 13,000 U
Variable overhead cost variance 3,000 F
Variable overhead efficiency variance6,500 F
Fixed overhead cost variance 3,000 F
When determining the total production cost flexible budget variance, what is the total manufacturing overhead variance of the company?