The following table represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely...

50.1K

Verified Solution

Question

Advance Math

The following table represents a project with four activities.All times are in weeks.

Activity

Immediate

Predecessor

Optimistic Time

Most Likely Time

Pessimistic Time

A

-

4

8

16

B

-

7

8

9

C

A

6

10

18

D

B

5

13

18

A. According to the data in the table. What is the criticalpath?

B. According to the data in the table, what is the minimumexpected completion time for the project?

C. According to the table there are four activities in theproject. Assume the normal distribution is appropriate to use todetermine the probability of finishing by a particular time. If youwished to find the probability of finishing the project in 21 weeksor fewer. It would be necessary to find the variance and then thestandard deviation to be used with the normal distribution. Whatvariance and standard deviation would be used?

D. According to the table, There are four activities in theproject. Assume the normal distribution is appropriate to use todetermine the probability of finishing by a particular time. Whatis the probability that the project is finished in 20 weeks orfewer.

Answer & Explanation Solved by verified expert
4.1 Ratings (601 Votes)
    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students