The following table lists the components needed to assemble an end item, lead times, and...

60.1K

Verified Solution

Question

Accounting

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.

imagea. If 23 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)

b. An order for the end item is scheduled to be shipped at the start of week 18. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)

\begin{tabular}{|l|r|r|r|r|r|r|r|r|} \hline Item & \multicolumn{1}{|c|}{ End } & \multicolumn{1}{|c|}{ B } & \multicolumn{1}{l|}{ C } & \multicolumn{1}{|c|}{ D } & \multicolumn{1}{|c|}{ E } & \multicolumn{1}{|c|}{ F } & \multicolumn{1}{c|}{ G } & H \\ \hline LT (wk) & 3 & 1 & 3 & 3 & 2 & 3 & 2 & 3 \\ \hline Amount on hand & 0 & 12 & 7 & 27 & 13 & 31 & 5 & 0 \\ \hline \end{tabular}

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students